Two-way integration scenario consists of two related integration. For example two-way Project Online⇔Planner integrations consists of Project Online⇒Planner and Planner⇒Project Online integrations.

While setting/updating synchronization schedule in two-way synchronization scenario, you are updating schedule for both scenarios.

In order to set individual schedule for each scenario perform the following:
- Open Integration Hub and navigate to Scenarios Tab.

- Find the problem scenario(s), click  ✔ and select Edit option from the context menu;

- Click "Advanced Edit"   in top right corner;

- Scroll down to Pol Source Processing and set needed time;

-Click Save button to apply the changes.