Health widget pack contains a set of widgets to measure portfolio and schedule quality against various project management metrics.
Downloads
Please note: For On-Premise installations EPM Pulse version 3.1 or above is required.
Installation
Health widget pack can be installed via Widget Management.
Package Content
This package contains the following widgets:
Widget |
Dashboard Types | Description |
Detailed Level 1 Tasks | - Portfolio - Project | Displays level 1 tasks that are not summary tasks or not milestones |
High Duration Tasks | - Portfolio - Project | Displays tasks whose baseline duration is too high. High duration threshold can be changed in the widget parameters, by default its value is 352 hours (44 days). Baseline to check tasks duration against can be also selected in the widget parameters, by default widgets uses Baseline 0 |
Low Duration Tasks | - Portfolio - Project | Displays tasks whose baseline duration is too low. Low duration threshold can be changed in the widget parameters, by default its value is 8 hours (1 day). Baseline to check tasks duration against can be also selected in the widget parameters, by default widgets uses Baseline 0 |
High or Negative Slack Tasks | - Portfolio - Project | Display tasks that have high or negative slack (float). High float threshold can be changed in the widget parameters, by default its value is 352 hours (44 days) |
Incomplete Tasks | - Portfolio - Project | Displays tasks that are not complete (i.e. those that don't have Actual Finish Date yet ) and have non-zero finish variance against selected baseline. Finish variance threshold can be changed in the widget parameters, by default its value is 0 hours. Baseline to check tasks against can be also changed in the widget parameters, by default widget uses Baseline 0 |
Milestone with Assignments | - Portfolio - Project | Displays milestones that have assignees |
Summary Tasks with Assignments | - Portfolio - Project | Displays summary task that has assignees |
Missing Baselines | - Portfolio - Project | Displays tasks that don't have baselines. Baseline to check tasks against can be selected in the widget parameters, by default widget uses Baseline 0 |
Task Assignment Issues | - Portfolio - Project | Displays tasks that have at least one of the following issues with their assignments: - “Unassigned” - task doesn't have an assignee - “Unknown Resource” - task has an assignee that doesn't exist in the Enterprise Resource Pool - “Local Resource” - task assignee is a local resource (i.e. resource that have been created in Project Pro, but not added to Enterprise Resource Pool) Issues that need to be checked can be selected in the widget parameters, by default widget verifies all of the listed issues |
Tasks with Actual Start in Future | - Portfolio - Project | Displays tasks whose Actual Start Date is in future |
Tasks with Blank Name | - Portfolio - Project | Displays WBS of the tasks that have blank names |
Tasks without Deadline | - Portfolio - Project | Displays tasks that don't have Deadline Date |
Portfolio Scorecard | - Portfolio | Displays number and percentage of projects that don't have: - Milestones - Assignments - Issues - Risks - Baselines - Status Date Widget also displays an indicator for each scorecard metric that became red in case if more than 20% of projects have issues. Each scorecard provided with a drill-down that opens a list of projects that have issues |
Resources with Zero Rate | - Resource Pool | Displays resources whose standard rate is 0 |
Resources without Role | - Resource Pool | Displays resources which role is not set |